DESIGN OF CIVIL WORKS PROJECTS FOR AENA NETWORK AIRPORTS

Design of more than 60 airside projects, including runways, taxiways, aprons and associated systems. Investment in excess of 800 million Euros, during the 2020-2025 period

PROJECT MANAGEMENT FOR THE DESIGN PHASE OF THE NEW PROCESSOR AND REMODELING OF T123 AT ADOLFO SUÁREZ MADRID BARAJAS AIRPORT

Project Management and Technical Direction of the T123 New Processor Building and Remodeling Project, estimated at 700 million euros, during the design development, bidding and transition period up to the construction works.

PROJECT MANAGEMENT FOR AIRPORTS IN THE BALEARIC ISLANDS REGION OF THE AENA NETWORK

Project Manager and supervision of all investments in the Balearic Islands Airports (Palma de Mallorca, Menorca and Ibiza) in the period 2018-2027 with more than 800 M€ of investment.

DEVELOPMENT OF AENA AIRPORT MAINTENANCE STRATEGIC PLAN

Strategic consulting to improve the efficiency of maintenance and asset management services. Including the following services. Digitalization, creation of scorecards and audits. Asset management; improvement of maintainability, life cycle optimization, replacement investment planning and improvement plan. Efficiency of economic management and knowledge management and continuous improvement. Define strategies and establish improvement processes. Audit plan; service compliance and asset condition

PROJECT MANAGEMENT OF ELECTRIC VEHICLE CHARGING POINTS IN THE AENA AIRPORT NETWORK

Project Management, Technical Project Management and Supervision of the INVESTMENT of electric vehicle charging points at all Aena airports, from the beginning of their feasibility to their commissioning, at all Aena Airports

ENAIRE PROJECT DESIGN (AIR NAVIGATION)

Design and supervision of all investments in physical infrastructure of the Air Navigation Manager ENAIRE during the period 2018-2024

DRAFTING OF PROJECTS AND SPECIFICATIONS FOR AENA AIR NAVIGATION PROJECTS

Drafting of projects or technical specifications to serve as the basis for the contracting of the different Air Navigation files (ILS, radars, Voice Communication Systems) for an amount of approximately 60 million euros within the framework of the AT Project Management (PM) contract and Project Drafting, Work Management and Control and Surveillance of the files for Air Navigation Installations.

DESIGN AND SUPERVISION OF THE ADAPTATION OF THE TERMINAL BUILDING TO THE FUNCTIONAL DESIGN OF AENA REUS AIRPORT

Detailed design and supervision of the execution of the Expansion of the Reus Airport Terminal Building, Project and Works Management, with a duration of 4 years, and with an investment of nearly 14 million euros, applying the BIM methodology.

DESIGN OF THE EXPANSION OF THE ACC BUILDING (AIR TRAFFIC CONTROL CENTER).

Expansion of ENAIRE buildings and critical facilities with a new pioneering controllers' room which contributes to the development of the management of 2 million flights per year and 2.2 million km2 of airspace. Investment: 15 million

PROJECT MANAGEMENT PARA LOS AEROPUERTOS DE LA REGIÓN CANARIAS DE AENA

Project Management and Supervision of all investments in the Canary Islands Airports in the period 2023-2027 with more than 500 M€ of investment. Undertaking of investments in Terminals and Aero Buildings

PROJECT MANAGEMENT FOR AENA'S NORTHERN REGION AIRPORTS

Project Manager, technical project management and supervision of all investments in 11 airports in Northern Spain (Bilbao, Santiago, ....) with more than 300 M€ of investment.

TECHNICAL ASSISTANCE TO AEROCAS AND TECHNICAL SUPERVISION OF THE OPERATION AND MAINTENANCE CONTRACT FOR CASTELLON AIRPORT

Consultancy for the supervision of the Castellón Airport Concession Company between 2015 and 2021 (maintenance, operations, services and investments) including the transition phase from the Concession to the Administration's own management
Since we started in 2010, our goal has been to provide customers with a comprehensive solution within the infrastructure sector. Today, having successfully completed more than 1,000 engineering projects in over 15 countries, we continue to eagerly embrace each new challenge. We are backed by a highly qualified team that is focused on continuous improvement and innovation, with the purpose of ensuring a satisfactory outcome in all our engineering projects: from projects in airports, urban works, or mobility, to technology and R&D projects, civil infrastructure, construction, infrastructure management, hydraulic and energy projects, and environmental projects.